Reasonable objection to a named specialist
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars. This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
There are two ways in which the specialist provisions operate:
- Pre-named specialist: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
The grounds for reasonable objection by the contractor could include:
- The specialist has a poor safety record.
- If there are reasonable grounds for believing that the specialist may not be financially secure, solvent, reliable or technically competent.
- If the tender sum is not believed to be financially viable.
- Where the programme is deemed to be unreasonable.
Similar provisions are permitted where the contractor is unable to enter into a contract with the named specialist, or where the contractor terminates the specialist’s employment.
If the contractor proposes their own specialist, the employer has seven days from the point at which the contractor notifies them of the proposed replacement to raise any reasonable objection themselves.
The employer may object to the proposed specialist on the grounds that there will be a sub-standard performance. However, since the contractor remains responsible for the performance under the contract, it is rare that such an objection would be deemed valid. Where the employer has a realistic concern that liquidated damages for any delay that arises due to sub-standard performance is an inadequate remedy, the objection may be judged to be reasonable. Likewise if the employer has concerns about the contractor having the resources to fulfil their obligations in the event of things going wrong.
In the event of an objection raised by the employer being deemed reasonable, the contractor must propose a further replacement for consideration.
Adjudication can be used if necessary to determine what constitutes a reasonable objection.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Construction contracts.
- Contract conditions.
- Extension of time.
- Joint Contracts Tribunal.
- Named specialist work.
- Named subcontractor.
- Nominated subcontractor.
- Subcontractor.
- Supplier.
External references
- ‘The JCT Major Project Form’, JONES, N. F., Blackwell Publishing, (2004)
Featured articles and news
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.